Like Never Before Weekly Update

What’s Happening?

The big dirt pile is gone! You will still see a stockpile of dirt up against the wall. That will become future back fill. All pad footings are done. Now it’s time for steel.

Check out the steel delivered September 5-6. Twelve truckloads in all. Steel starts going up the week of September 9. Over the next 2 weeks, the building will start to take shape right before our very eyes.

In Building B, the 2nd floor of our Children’s Ministry remodel, the installed dry wall is giving such a sense of the great new space. Electrical is being worked on. Carpenters are busy up there, too.

Financial Update

Approximately $66,852 was given during the week ending September 1. We are amazed and grateful at all God is doing through his grace toward us and your generosity.

Resources

Visit our Resources page at the following link to see the latest construction update videos, photos, building renderings, and even a playlist: https://likeneverbefore.wacc.net/resources/