Like Never Before Weekly Update

What’s Happening? 

Construction on the new worship center encountered more rain delays. So this week, the time was given to dry out the ground. If all goes well, the slab of cement for the floor will be poured on Saturday. The exciting news is we will be given an opportunity this Sunday, Dec. 15, to walk on to the floor and take a closer look. That sounds exciting! This will help everyone get a sense of the structure soon to house our worship gatherings.

In Building B, the renovation of the first floor continues to move ahead on schedule. Work was done in the heating and air conditioning system. Preparations for painting are wrapping up. Things are going well.

Financial Update

We are thankful for God’s generous provision as our WACC family responds to the need. People continue to fulfill their commitments for the Like Never Before building opportunity, and that is such an encouragement. Approximately $39,588 was given during the week ending December 8.

Resources

Visit our Resources page at the following link to see the latest construction update videos, photos, building renderings, and even a playlist: https://likeneverbefore.wacc.net/resources/