Construction continues and the crews are following physical distancing guidelines, hand washing protocol, and other safety measures. 

What’s Happening?

New Worship Center 

Similar to last week, taping, framing, and roughing in are still in process. Framing in the front lobby, installing refrigerant piping, putting foam in at the risers, and framing the angled walls in the vestibule continued this past week. Some roofing is going on both of the low roofs.

Building B1, Future Nursery

Outside, alongside the new ramp into the new nursery area, the seat wall footings were dug. Inside, mechanical work for hanging ducts has begun. The electricians are drilling for wires.

Generosity Update

In these uncertain days, your continuing generosity is so appreciated. God continues to provide, and our WACC family continues to respond to the needs. Approximately $22,229 was given toward the Like Never Before building project during the week ending March 29.

Resources

Visit our Resources page at the following link to see the latest construction update videos, photos, building renderings, and even a playlist: https://likeneverbefore.wacc.net/resources.